COMPARISON : Flourescent /TL 42W Vs LED Tube 14W


  COMPARISON  : Flourescent /TL 42W  Vs  LED Tube 14W    
  Description Unit LED TUBE KONVENSIONAL
  17W 40W
  DATA

       
 
A. Lamp Figure              
1 Number of Luminaires   point   1.00
1.00
2 Number of lamp per luminaire pcs   4.00
4.00
3 Actual Energy Consumption/lamp watt   17.00
45.00
4 Total Energy Consumption/Luminaire watt   68.00
180.00
5 Lamp life time (hours)   hrs   50,000.00
8,000.00
6 Lamp life time (months)   month   69.44
11.11
7 Lamp life time (year)   year   5.79
0.93
                   
B. Lamp Price              
1 Lamp price 
  Rp   435,000.00
50,000.00
2 Ballast

  Rp    
30,000.00
3 Initial cost for lamp & gear/pc Rp   1,740,000.00
230,000.00
                   
C. Installation Cost              
1 Installation cost per-luminaire (per point) Rp   100,000.00
100,000.00
                   
D Manitenance Cost              
1 Lamp replacement cost   Rp   20,000.00
20,000.00
2 Ballast & starter replacement cost Rp    
 
                   
E Assumption
1 Running hours/year 24 Hr/day Hrs   8,640.00   8,640.00
2 Energy Cost Rp/kWhr-WBP   Rp   1,200.00   1,200.00
                   
F Initial Cost Analysis (per year)
1 Total initial cost for lamp & gear/pc Rp   1,740,000.00   230,000.00
2 Total initial cost for installation Rp   100,000.00   100,000.00
3 Total initial cost
  Rp   1,840,000.00   330,000.00
4 Extra initial investment Rp       1,510,000.00
                   
G Running Cost Ananlysis (per year)
1 Energy cost of all lamps/year Rp   705,024.00   1,866,240.00
2 Lamp cost all of lamps/year   Rp   0.00   216,000.00
3 Lamp replacement cost all of lamps/year Rp   0.00   86,400.00
4 Total running cost of all lamps/year Rp   705,024.00 2,168,640.00
5 Saving in running cost/year Rp       1,463,616.00
                   
H Result
1 Finance Indicator:              
  a. Extra initial investment   Rp       1,510,000.00
  b. BEP

  Year       1.03
  c. BEP

  Month       12.38
   

           
2 Environmental Indicator:            
  a. Power consumption/year   kWh   587.52 1555.2
  b. Reduced Power Consumption %       62.22%
                   
















































































MENGHITUNG LISTRIK 3 PHASE


 
 
           
               
               
                                  P  = V X I x 1,73 x cos Q    
               
 
 
           
    VA Tersambung : 33,000 VA 33.0 kVA  
    Watt Tersambung : 29,700 Watt 29.7 kW  
 




Tegangan : 380 Volt.      
    Cos j : 0.90




     
 




Beban Terpakai : 26400 VA 26.4 kVA  
               
    I Beban: 40.11 Amp      
    Kapasitas MCB : 50 Amp      
    Kapasitas Kabel : 16.0 mm²      
    VA Terpakai: 26,400 VA      
    Beban Terpakai: 23,760 Watt      
    VAR Terpakai: -11,507 VAR      
               
    Pemakaian kWh :          
    LWBP : 213.8 kWh / Hari    
    WBP : 71.3 kWh / Hari    
    TOTAL : 285.1 kWh / Hari    
    TOTAL Pemakaian 1 Bulan : 8,554 kWh / Bulan    
               
     Jam Operasional : 12 Jam      
    LWBP : 9.00 Jam      
    WBP : 3.00 Jam      
    Hari dalam 1 Bulan : 30 Hari      
               
  Note : VA ( Daya Semu )          
            Watt ( Daya Nyata )          
            VAR ( Daya Reaktif )          
               
 






               
enis Pengerjaan - Jangka Pendek Biaya (Rp) Keterangan

# Pengerjaan Instalasi Client
Instalasi Linux Client + Short Training 100.000 Exclude CD/DVD Linux
Instalasi Windows 50.000

# Pengerjaan Jaringan Komputer
Memasang kabel dari switch ke Komputer (Lokasi Datar) 50.000 Exclude Kabel UTP Rp. 1.5rb/feet
Memasang kabel Backbone Switch-Switch (Lokasi Datar) 60.000 Exclude Kabel STP Rp. 2rb/feet
Memasang Wifi per titik 200.000 Exclude Kabel UTP Rp. 1.5rb/feet
 
# Pengerjaan Jaringan Telepon
Memasang kabel dari telpon ke PABX (Lokasi Datar) 30.000 Exclude Kabel 2 wire Rp. 2,5rb/mtr
Memasang kabel Backbone PABX-PABX (Lokasi Datar) 60.000 Exclude Kabel 4 wire Rp. 3,5rb/mtr
Hanya Setting PABX 30.000 Setting per Line/Ext PABX
 
# Pengerjaan Membangun Server
Instalasi Windows untuk Server 200.000
Instalasi Linux untuk Server 300.000
Web Server Nginx+PHP-FPM+PostgreSQL 800.000
Server untuk Monitor Jaringan dan Server 1.000.000
File/Data Server 1.000.000 Harga utk maks 10 user
Proxy/Internet Server+Autentikasi 1.000.000 Maks 100 user
VoIP Server 1.000.000
Accurate Server Berbasis Linux 300.000

# Membuat Website Negosiasi
 
# Transportasi (Darat)
Depok, Citayam 20.000 per Kedatangan/Orang
Kota Bogor, Jakarta Selatan 30.000 per Kedatangan/Orang
Jak-Ut, Jak-Bar, Jak-Pus 50.000 per Kedatangan/Orang
Tangerang, Bekasi 80.000 per Kedatangan/Orang
Daerah Lain Negosiasi per Kedatangan/Orang
 
# Biaya Garansi Pengerjaan (Maksimum 1 tahun)
Untuk proyek Rp 0-30jt selama 2 bulan Free
Harga Pengerjaan Rp 0-3jt selama 3 bulan 100.000
Harga Pengerjaan Rp 3-7jt selama 3 bulan 200.000
Harga Pengerjaan Rp 7-15jt selama 3 bulan 300.000
 
 
Jenis Pengerjaan - Jangka Panjang (Minimum 3 Bulan) Biaya (Rp) Keterangan
Maintenance Komputer Klient Tiap 2 minggu 20.000 per Komputer, Minimal 15 User
Maintenance Server 500.000 Maks File+Database 2 GB
Maintenance Jaringan Komputer Tiap minggu 150.000 Maks 30 User
Posting artikel + Spreading (sumber artikel dari pemilik) 1.500.000 Maks 300 artikel/bulan
Monitoring Jaringan dan Server+ Pelaporan 500.000 Maks 10 Titik
 
 
Training Biaya (Rp) Keterangan
Training Linux Untuk Pemula
Info: www.cobalinux.co.cc

- Pekerjaan yang tidak tertulis pada tabel di atas dapat dikonsultasikan via email: info[at]jaringankantor.com.

- Untuk pengadaan barang-barang dapat ditanyakan via email: info[at]jaringankantor.com

- Harga dapat berubah sewaktu-waktu tanpa pemberitahuan lebih lanjut.